Fabrication start of sub-station at STX France

Rentel electric sub-station (Sketch: STX France)
With the design phase completed, the first steel cutting of the sub-station for Rentel’s Belgian field has started. The engineering, procurement, construction and installation contract, signed in April 2016, covers the equipment engineering, fabrication, transport and installation. Delivery and installation at sea is scheduled in spring 2018. Fabrication of the structure will last several months and will take place mainly at STX France’s Anemos yard, dedicated to offshore energies.